Tuesday, March 24, 2009

Facilitating a Fact-Based Discussion

At election time every year there are healthy discussions on what the City has done or should be doing. Some of the topics currently being considered are the City’s tax rate, the level of debt, and spending on two capital projects: the Rails to Trails, and the 1919 building. Let’s explore these topics to facilitate a fact-based discussion.

Tax Rate
The City’s tax rate for the current fiscal year is 7.3277 mills. An examination of City budget history reveals that the tax rate approved by the City Commission for the current fiscal year is the lowest tax rate in 17 years! The tax rate for FY ’91-92 is the next lowest. As noted in a previous column in this space, in the last four years the City Commission has reduced the City’s property tax rate 22%.

City Debt
There has been much discussion on the level of City debt, but I have yet to hear anyone mention how our City’s principal debt amount (i.e., the amount owed on the original borrowed amount, without adding in interest payments) compares to that of other similar cities. The cities of Auburndale and Haines City are often used for purposes of comparison. For the 2007-2008 Fiscal Year, these three cities ended the fiscal year with these respective amounts of principal debt:

  • Auburndale - $54,143,338

  • Haines City - $45,360,648

  • Lake Wales - $32,725,486

Lake Wales has the lowest principal debt amount of the three cities.

In this space I have noted before that debt is a necessary method of providing funding for large capital projects.
Rails to Trails
The first phase of this project was a Florida Department of Transportation project, and no city funds were involved. That section of trail begins at Fourth Street and ends at Kiwanis Park.

The extension of the Trail to Buck Moore Road was a City project, paid for with grant funds that required a match of $133,000. The matching amount came from City Recreation Impact Fees, which can only be used to expand or provide new recreation facilities.

1919 Building (Hardman Hall)
The 1919 building project started with high hopes after the property was acquired from the county school board in 1995. An article in this newspaper on June 8, 1995 stated that the buildings would be renovated with funding “…from a variety of sources in the form of grants.” It was also noted that “… the entire project cannot be completed at one time but can be done in phases.”

To date, three of the buildings have been restored, with grant funding for one of the buildings, the former elementary school being leased to the Boys and Girls’ Club. The Club paid the matching funds required for that restoration grant. The other two restored buildings, the Kirkland gym and the Little Theatre, were restored with City bond proceeds and (non-city) funds raised by the Little Theatre, respectively.

The 1919 building has to date utilized $1,869,711 in grant funds and $300,000 in Community Redevelopment Agency (CRA) funds towards rehabilitation. There have also been $154,285 in private donations and $17,124 in other city funds used for the project. The next phase of restoration is currently being planned, and it will use $350,000 in grant funds and $300,000 in CRA funds. Beyond the next phase, it is estimated that it will take $1,011,087 to open the building for use and another $712,787 to completely finish the building, grounds, and parking. The spreadsheet detailing all of these figures (as well as the City budget and millage history noted above) is now available on the City’s website at http://www.cityoflakewales.com/.

The City Commission has established an advisory committee to work on the fund-raising needed to complete this building. Applications for membership are available at the City Clerk’s office.

It is anticipated that when this magnificent structure is completed its focus will be on musical education and performance. Lake Wales has a long tradition of musical excellence at our High School. The recent establishment of McLaughlin Middle School as a “School of the Arts”, and the strong music program being built at Bok Academy will greatly enhance this tradition. We look forward with the vision of the new advisory committee raising the remaining dollars necessary for our children to learn and perform at this wonderful new facility, which will richly add to the definition of our community as a place for both the arts and education.

Tuesday, May 27, 2008

More Project Updates

Last week in this space we reviewed a progress report on a number of high-profile projects, both public and private. There are other public projects underway as well, so let’s take a look at a few more!

Hardman Hall (the 1919 building)
Work continues on this project. The contractor has finished the masonry work on a section of the south exterior wall that was failing, and the wall was taken down and put back up using the same exterior bricks. The remodeling work funded by the Phase 4 historic preservation grant is now complete, and work on the Phase 5 grant should be completed by the end of June. The phase 6 grant is scheduled to start in July and will focus on the installation of drywall and other improvements on the first floor.

This $4.6 million project is being funded with a combination of grants, CRA funds, and donations, and work has progressed as grant funds have become available. As discussed at the public meetings held in the building last March, $907,236 has been secured toward the remaining $2,373,875 in project costs, leaving $1,466,639 yet to be raised. Dr. Gabe Statom has been hired to assist in the fund-raising efforts and to prepare the programming for the building.

Planning is underway for this building to become:
  • The home auditorium of the Lake Wales Chorale and the Youth Chorale;

  • A venue for concerts by a variety of artists;

  • A music education center, reflecting the long tradition of musical excellence in school band performance.
You are cordially invited to join in these efforts that will have far reaching benefits for our community!

Rails to Trails
Funding for the second phase of the Rails to Trails project has been awarded by the Office of Greenways and Trails. The grant award of $200,000 is matched with $133,000 from City recreation impact fees, which are restricted funds that can only be spent on the expansion of recreation facilities. This section of the trail will be built from Kiwanis Park to an area west of Buck Moore Road. It is anticipated that the City will hire the contractor for this work with the contract forbidding the use of vibratory compactors. Again, per the ordinance adopted by the City Commission, contractors with unresolved complaints from City residents will not be eligible to compete for this work.

City staff is checking on the possibility of extending the contract with the asphalt company that is doing the City’s resurfacing work for the construction of the trail. A schedule for the project will be released at that time.

The design of this section of the trail will include the construction of a fence for a portion of the north side of the trail, as well as posts at certain points, to discourage motorized vehicle riders.

CSX Building
The former high school agriculture building on Scenic Highway near Kissimmee Ave is undergoing a facelift. The exterior of the building is being restored to its original look, and inside the restrooms have been renovated. A visitor welcome center room has also been created, to be staffed by volunteers, for area visitors and persons using the trail. The remainder of the building will continue to be used by the City’s parks and streets divisions for offices and equipment storage. Funding for this project is provided by a historic preservation grant which was matched with insurance proceeds that were used to repair hurricane damage.

Re-development activities on Lincoln Avenue
The Community Re-Development Agency has acquired several properties on Lincoln Ave over the past few years. One of these properties is referred to as the Walker Building at the corner of Lincoln Ave and C Street. The CRA’s re-development contractor, Kimbrough and Associates, is exploring the feasibility of using the building for apartments and offices. Recently the interior furnishings on the first floor were removed. In addition, both the Walker building and the barber shop building (under private ownership) were painted using colors from a palette provided by the architect hired to assist in this project. In addition, across the street from the Walker building, a new meat store has opened.